Master plan setup – Use futures date as requirement date
pl-PO Use Futures date as Requirement date = Yes
|
pl-PO Use Futures date as Requirement date = No
|
pl-PO + pl-Prod Use Futures date as Requirement date = No
|
Coverage group – Action Basis Date
Action Basis date = Requirement date
|
Action Basis date = Futures date
|
Test cases
Scenario
Sales order with confirmed delivery date: 16.11.2016; the lead time setup of the purchase item (M0009) doesn’t allow the PO to be on time.

pl-PO Use Futures date as Requirement date = Yes; Action Basis date = Requirement date

pl-PO Use Futures date as Requirement date = Yes; Action Basis date = Futures date

pl-PO Use Futures date as Requirement date = No; Action Basis date = Requirement/Futures date
Note: Changing Action Basis date does not have an affect

pl-PO + pl-Prod Use Futures date as Requirement date = No; Action Basis date = Futures/Requirement date
Note: Changing Action Basis date does not have an affect

Recommendation
USE: Use Futures date as Requirement date = Yes; Action Basis date = Requirement date
With this setting the system tells you what is late and what you should try to do about it.